As part of our preventative maintenance measures, a routine impedance test is required on the battery stack in order to test overall battery health and ensure future performance and capacity; therefore our engineers will be performing battery tests on our power feeds.

During this 2-leg maintenance, the UPS will need to be taken offline in order to test the batteries meaning any customers that solely use this feed will be at risk from a possible mains failure.


---- LEG 1 -----

- At Risk Window Start: 21/02/2018 - 09:15 GMT

- At Risk Window End:  21/02/2018 – 16:45 GMT

---- LEG 2 -----

- At Risk Window Start: 22/02/2018 - 09:15 GMT

- At Risk Window End:  22/02/2018 – 16:45 GMT



If you have any questions or queries please contact our support department by raising a ticket.